DELAY RISK ANALYSIS OF PT ADARO INDONESIA CONSTRUCTION PROJECT - CASE STUDY ON PT ADARO INDONESIA TABALONG WATER AND MUD INSTALLATION PROJECT

Authors

  • Damar Septiawan Megister Civil Engineering Study Program, Faculty of Engineering, Lambung Mangkurat University, South Borneo, Indonesia. Author
  • Dan Irfan Prasetia Megister Civil Engineering Study Program, Faculty of Engineering, Lambung Mangkurat University, South Borneo, Indonesia. Author

Keywords:

Drainage Installation, Sump Water, Risk Factors, FMEA, Strategy, Mitigation

Abstract

In 2019, PT Adaro Indonesia carried out a program of installing aramco culverts with a diameter of 3 meters and construction of gabions at the inlet and outlet sections at Sta 70+200 HW, to replace the function of culvert construction at Sta 70+300 HW which was no longer functioning. well. However, the condition of the aramco culvert installation construction project and gabion construction, as of February 2, 2020, is still in the form of construction progress of 90.62%. Even though the planned target is to start on July 29, 2019 and finish on September 29, 2019. In this project, there are several factors that are thought to affect project delays. This research was conducted to find the real causes of the constraints on the project. This study used a questionnaire and interview instruments. Respondents were selected with the assumption that they had been involved in or worked on a sump and mud drainage installation project. The data is then tested and after being declared valid and reliable then analyzed using the FMEA (Failure Modes and Effects Analysis) method. The results showed that 3 items became the dominant project risk factors, namely the risk of project failure due to changes in planning and specifications (RPN 706.90), Project failure risk due to no project delay penalty (RPN 633.70), Project failure risk due to late delivery of materials to the site (RPN 436.67). Based on the foregoing, further observations and interviews were conducted to obtain mitigation recommendations as a strategy to minimize the potential risk of project failure. The proposed risk mitigation strategy is with careful planning with observations in accordance with actual field conditions, using a professional/competent third party (planning consultant) in planning and design, using the Procrument Road method in the form of Design and Build, a binding contract is enforced between the implementer and the contractor. owner, include in the contract documents related to the penalty scheme that must be accepted by the vendor if the project experiences delays or failures, applies more stock of stone material for gabion work and applies more than 1 river stone supplier selection.

References

Alifen, R. S., R. S. Setiawan., A. Sunarto. 2000. Analisa “What If” Sebagai Metode Antisipasi Keterlambatan Durasi Proyek, Dimensi Teknik Sipil Vol. 2 No. 1.

Andi, A., S. Susandi., H. Wijaya. 2003. On Representing Factors Influencing Time Performance Of Shop-House Contructions In Surabaya, Dimensi Teknik Sipil Vol. 5 No. 2

Assaf, A. 1995. Causes of Delay in Large Building Construction Projects, Journal of Management in Engineering.

Astina, Dhian C. N., Ida A. R. W., dan I. G. P. Joni. 2012. Analisis Faktor-Faktor Penyebab Keterlambatan Pelaksanaan Pekerjaan Proyek Konstruksi Di Kabupaten Tabanan, Jurnal Ilmiah Elektronik Infrastruktur Teknik Sipil.

Bakhtiyar, Ariful., Agoes S., dan M. H. Hasyim. 2012. Analisis Faktor-Faktor Yang Mempengaruhi Keterlambatan Proyek Konstruksi Pembangunan Gedung Di Kota Lamongan, Jurnal Rekayasa Sipil Volume 6, No. 1 – 2012 ISSN 1978 – 5658.

Dewi, Dian, A. N. N. D. 2018. Modul Uji Validitas dan Reliabilitas, Diponegoro University, (https://www.researchgate.net/publication/328600462 quoted on February 16, 2019 at 17.24 WITA).

Guilford, J. P. (1956). Fundamental Statistics in Psychology and Education. New York: Mc Graw-Hill Book Co. Inc.

Iin, Hurin. 2017. Manajemen Risiko Teknologi Informasi Pada Proyek Perusahaan Xyz Melalui Kombinasi Cobit, Pmbok, Dan Iso 31000, Tesis, Sepuluh Nopember Institute of Technology, Surabaya.

Joni, I. G. Putu. 2012. Resiko Manajemen Proyek, Jurnal Ilmiah Teknik Sipil Vol. 16, No. 1.

Lestari, I. Indah., dan Toni Mindra. 2019. Analisis Korelasi Rank Spearman Atribut Produk Terhadap Keputusan Pembelian Spare Part di Bengkulu (Survey pada Global Motor Bengkulu), Jurnal Ilmiah Akuntansi, Manajemen & Ekonomi Islam (JAM-Ekis) Volume 18, Nomor 1.

Murtani. 2017. Analisis Faktor-Faktor Kendala Proyek pada Pembangunan Pelabuhan Swarangan-Pelaihari, Tesis, Universitas Lambung Mangkurat, Banjarmasin.

Nasution, A. H. 2008. Manajemen Industri, Penerbit Andi, Yogyakarta.

Pertiwi, Havea. 2017. Implementasi Manajemen Resiko Berdasarkan PMBOK Untuk Mencegah Keterlambatan Proyek Area Jawa Timur (Studi Kasus: PT. Telkom), Jurnal Studi Manajemen dan Bisnis Vol 4 No.02.

Proboyo, B. 1999. Keterlambatan Waktu Pelaksanaan Proyek : Klasifikasi Dan Peringkat Dari Penyebab-Penyebabnya, Dimensi Teknik Sipil Vol. 1 No. 2

Pratama, Dedi., dan Irfan Prasetia. 2019. Prevention Strategy of The Delivery of Construction Projects in Feces Mud Processing Infrastructure Development, American Journal of Engineering Research (AJER) vol.7, no.12, pp. 132-138.

Sakinah, Baiq Farida. 2015. Analisis Penyebab Keterlambatan pada Pekerjaan Konstruksi Jalan Kabupaten Lombok Tengah dengan Metode Analisa Faktor, Jurnal, Brawijaya University.

Saputra, Ramdhan Yudndra. 2017. Analisa Faktor Penyebab Keterlambatan Penyelesaian Proyek Pembangunan Mall ABC, Tesis, Sepuluh Nopember Institute of Technology, Surabaya.

Syarifudin, S. Widodo., dan Arif Nurwaskito. 2017. Kajian Sistem Penyaliran Pada Tambang Terbuka Kabupaten Tanah Bumbu Provinsi Kalimantan Selatan, Jurnal Geomine, Vol. 5, No. 2.

Widhiasari, Pieta., dan Irfan Prasetia. 2018. Risk Analysis Analysis of Cantilever Wall and Sheet Pile as River Cliff Reinforcement Methods, American Journal of Engineering Research (AJER), vol.7, no.12, pp.190-194.

Wijayanthi, Shanty. 2005. Faktor-faktor Penyebab Keterlambatan Waktu Pembangunan Proyek Gedung Negara di Lingkungan Pemerintah Kota Kediri. Sepuluh Nopember Institute of Technology, Surabaya.

Downloads

Published

2021-07-09

How to Cite

DELAY RISK ANALYSIS OF PT ADARO INDONESIA CONSTRUCTION PROJECT - CASE STUDY ON PT ADARO INDONESIA TABALONG WATER AND MUD INSTALLATION PROJECT. (2021). INTERNATIONAL JOURNAL OF CONSTRUCTION ENGINEERING (IJCE), 4(1), 16-26. https://mylib.in/index.php/IJCE/article/view/IJCE_04_01_002